The restoration work is going to continue.

There is new scaffolding on the south side of the St. Peter and Paul´s Church in Kralovice. The restoration work is going to continue by repairing the vitrages and parts of the brick facade on the south side of the main nave. The action is financed by 690.000,-CZK from the Programme of the rescue of architectural heritage of the Czech cultural ministry. The Kralovice parish is going to ask the Town of Kralovice for a financial contribution for paying a part of the share of the property owner. The final costs are going to be 768.324,-CZK.

The Král PM Centrum Company is going to do the restoration of the facade under control of Helena Štěrbová. The restoration of the vitrages is going to be carried out by Art studion Monika Zborníková Vintrová.


On Thursday 30th July, two vitrages from two windows on the south side of the church were removed and taken to the restoration studio for repairing.